The firms that design and build data centers, and what each risks

A data center takes a dozen or more specialist firms, each with its own piece of the promise that the servers never stop. Here is what each one does on these projects and where claims against them tend to come from.

Why it matters

One building, one promise, many firms

Data centers are designed around uptime. Uptime Institute’s Tier III standard requires that equipment can be replaced and maintained with no shutdowns, and Tier IV adds fault tolerance on top.[1] Every discipline below contributes to whether the building keeps that promise.

When it does not, the cost is large. In Uptime’s 2024 operator survey, 54% said their most recent serious outage cost more than $100,000, and one in five said it cost more than $1 million.[2] Insurance trade reporting says insurers are now focusing on design exposure tied to geotechnical studies, drainage, permitting, power generation and cooling.[4]

In the cards below, the “where claims come from” notes are sourced where a source exists. Where they say “our practical view”, that is our experience placing coverage for technical firms, not data.

By discipline

What each firm does, and where claims come from

01

Electrical engineers

On a data center: Utility service, medium voltage distribution, generators, UPS and transfer schemes, designed to a redundancy target such as Uptime’s Tier III, which requires no shutdowns for maintenance, or Tier IV, which adds fault tolerance.[1]

Where claims come from: Power is the most common cause of serious outages in Uptime’s survey data, with UPS problems the most frequent single source.[2] A broker’s risk profile lists electrical distribution, redundancy configuration and UPS and battery integration among typical design error areas.[3]

Electrical engineers

02

Mechanical and HVAC engineers

On a data center: Cooling plant, air handling and, increasingly, liquid cooling to the rack. Heat loads drive the whole building.

Where claims come from: HVAC load calculations appear on the same broker’s list of typical design errors.[3] One law firm notes a designer can meet the standard of care and still face a claim if a contract’s performance requirement is not met.[5]

Mechanical and HVAC engineers

03

MEP engineers

On a data center: Firms that carry mechanical, electrical and plumbing together, often as the engineer of record for the whole building systems package.

Where claims come from: Coordination failures and scope ambiguity are among the main drivers of professional liability claims on these projects, according to insurance trade reporting.[4]

MEP engineers

04

Structural engineers

On a data center: Long span halls, roof loads from mechanical equipment, and slabs that carry heavy racks and must meet tight flatness tolerances, often stricter than FF 50 / FL 35.[6]

Where claims come from: Structural design is on the broker’s list of design error areas.[3] Our practical view: heavier liquid cooled racks change floor loads after design, which makes the load basis worth writing down.

Structural engineers

05

Civil and site engineers

On a data center: Grading, drainage, roads and utility routing on large campuses, often on greenfield land.

Where claims come from: Insurers are focusing on design exposure tied to drainage and permitting on these projects.[4] One insurer notes that a data center installation alters a property’s natural drainage patterns and can affect groundwater.[7]

Civil engineers

06

Geotechnical engineers

On a data center: Site investigation and foundation recommendations for heavy buildings, yards of generators and substations.

Where claims come from: Geotechnical studies are on the list of exposures insurers watch.[4] A contractors’ association guide warns that owners may look to cut corners in geotechnical work, which can create liability exposure.[8]

Geotechnical engineers

07

Fire protection engineers

On a data center: Detection, suppression and separation for rooms full of IT equipment and batteries. NFPA 75 sets minimum requirements to protect IT equipment and its rooms from fire, smoke, heat and water.[9]

Where claims come from: Our practical view: water and smoke damage to equipment that did not burn, and disputes over which code edition applied. Batteries are covered in our power and energy guide.

Fire protection engineers

08

Commissioning agents

On a data center: Testing from factory witness tests through integrated systems testing, where engineers simulate a utility outage and confirm generators start and take over.[10]

Where claims come from: Our practical view: owners rely on commissioning reports to prove redundancy works, so an outage after turnover often brings the commissioning scripts into the claim. More in commissioning and integrated systems testing.

Commissioning agents

09

Acoustic consultants

On a data center: Noise studies for rooftop fans, chillers and generators against local limits, often before a zoning hearing.

Where claims come from: Residents near data centers in Prince William County, Virginia, have complained publicly about constant noise.[11] Our practical view: a study that predicted compliance becomes evidence when neighbors complain.

Acoustic consultants

10

Scanning and BIM firms

On a data center: Laser scanning and models of existing halls before a retrofit. In one scanning firm’s case study, a university data center had little to no as-built documentation before it was scanned.[12]

Where claims come from: Our practical view: a model others design from, with no stated accuracy or limits, invites claims when equipment does not fit.

3D laser scanning · BIM coordination

11

Cost and scheduling consultants

On a data center: Estimates, schedules and project controls for owners and lenders on fast moving, very large budgets.

Where claims come from: Our practical view: a schedule or estimate relied on for a lease commitment or a financing decision. Delay is covered in schedule pressure and delay claims.

Cost estimators · Scheduling consultants

12

Environmental and permitting consultants

On a data center: Site assessments, wetlands and stormwater, and air permits for backup generators. Virginia alone listed 177 data center air permits in November 2024.[13]

Where claims come from: Permitting is one of the exposures insurers are focusing on.[4] Our practical view: a permit assumption that turns out wrong can stop a project.

Environmental consultants · Permit expeditors

13

Contractors and design-builders

On a data center: The general contractor, construction manager or design-build entity that holds the owner contract and hires the trades and often the engineers.

Where claims come from: A broker’s risk profile notes that a general contractor or design-builder can take on vicarious liability for a subcontracted designer’s errors.[3]

Design-build firms · General contractors

Before you sign

Five questions for any firm on the team

  1. Which redundancy target applies, and is it written into my scope or only into the owner’s requirements?
  2. Am I designing to a performance guarantee, or to the standard of care?
  3. Who coordinates between disciplines, and is that in anyone’s scope?
  4. Whose insurance schedule applies to me: the owner’s, the contractor’s or the design-builder’s?
  5. What limits are asked for, and do they fit what my firm carries?

The answers usually sit in the owner’s contract. See the clauses in hyperscaler and colocation contracts.

Our practical view

What to put in a data center proposal

Whatever your discipline, a few lines in the proposal do a lot of work later:

  • Name the design basis you were given: load, redundancy target, rack density. If it changes, it is a change.
  • Say what you are not doing, especially coordination with disciplines outside your contract.
  • Say whether you are designing to the standard of care or to a guaranteed result. A law firm writing on these projects warns that a performance requirement can create liability even when the design met the standard of care.[5]
  • Ask for the insurance requirements before you price the work, not after award.

Higher limits and project policies are covered in practice policies, project policies and limits, and the design side in MEP and electrical design liability.

For your firm

Is your data center scope on your application?

Carriers ask about it. Tell us your discipline and the project, and we will tell you how to describe it and what limits fit.

Common questions

Data center teams, in plain words

Which firms carry the most risk on a data center?

It depends on the scope and the contract. Power is the most common cause of serious data center outages in Uptime Institute’s data, which puts electrical design and commissioning close to the costliest failures, but every discipline on the list above has seen claims on large projects.

Is a data center claim different from any other building claim?

Often in size. In Uptime’s 2024 survey, 54% of operators said their most recent serious outage cost more than $100,000 and one in five said more than $1 million. Downtime losses fall on tenants as well as the owner.

Does my professional liability policy cover data center work?

Most professional liability policies are not written project by project, but whether a claim is covered depends on the policy wording and the facts. Some carriers ask specific questions about data center work, so describe it on your application.

We are a subconsultant. Does that lower our exposure?

Not necessarily. You may be bound by the prime contract through flow-down clauses, and the firm above you may look to you if a claim reaches them. Read the prime contract terms that apply to you.

Keep reading

Sources

  1. Uptime Institute Journal, “Explaining the Uptime Institute’s Tier Classification System” (Uptime is a data center certification and advisory firm)
  2. Uptime Institute, Annual Outage Analysis 2025, press release
  3. RT Specialty, Data Centers construction professional risk profile (a wholesale insurance broker)
  4. Insurance Business, “The hidden liability risks behind America’s data center expansion”
  5. MG+M, professional liability risks for design professionals on data center projects (a law firm)
  6. Intertek, on floor flatness in data centers (a testing and inspection company)
  7. Ascot Group, “Mitigating data center environmental risk” (an insurer)
  8. Associated General Contractors, “Insurance Issues in Constructing Data Centers: A GC’s Perspective”
  9. NFPA 75, Standard for the Fire Protection of Information Technology Equipment (2024 edition)
  10. Hioki, “Data Center Commissioning and 5 Levels of Testing” (a test equipment maker)
  11. DatacenterDynamics, “Prince William residents complain of ‘catastrophic’ noise from data centers”
  12. GPRS, case study: laser scanning and BIM for the Tufts University data center renovation (a scanning services company)
  13. Virginia Mercury, “Virginia environmental regulators make info on data center operations more publicly accessible”

General information only, not legal advice, current as of November 2026. Descriptions of each discipline’s work are general; your scope is what your contract says. Whether a claim is covered depends on the facts and your actual policy wording.

Talk to a specialist

Tell Us About Your Firm. We’ll Tell You What We See.

Starting out or renewing, with a policy in hand or not. If something is worth discussing, we’ll call. If not, we’ll say so.