The change orders nobody would pay
An architect hired the mechanical engineer as its own sub-consultant. Ductwork ran into ceilings and steel, and the owner demanded the cost of the change orders from the architect. A spec requiring shop drawings and a mediation clause helped. Months of silence made the owner angrier.
Answer early, even to deny. And keep the paper that shows who was responsible for what.