Restroom renovationThe job worth walking away from
Declinethe risk manager’s advice, before any contract was signed
A client would only pay to renovate two of four restrooms, which conflicted with code and accessibility rules. The firm wanted the client to indemnify it. The risk manager pointed out that the likely claimant was a member of the public, so an indemnity from the client wouldn’t solve the problem.
If you know a design won’t meet code, a contract clause can’t fix it.
Oceanfront custom homeThe site changed. The claim came anyway.
$10M+home value, designed years earlier
Years after the design, erosion changed the site. The design team was brought into a claim that the underwriter described as costly. She noted that, in general, the larger the house, the larger the claims tend to be.
High-value residential work carries high-value claims.
Landscape architectureA planter that outgrew its pot
Paidthe claim was paid
A landscape architect specified decorative planters that cost thousands of dollars each. A plant outgrew its pot and broke it, the firm was sued, and the claim was paid.
What you specify and recommend is part of your design.
Delay claim defenseHundreds of changes, none paid
800changes on one project, the panel’s example
Asked whether unlimited construction administration hours make tracking pointless, the risk manager said no. A record showing hundreds of changes explains why a schedule slipped, even if none of them earned a fee.
Keep the change log even when nobody is paying for the changes.