Managing Scope Creep

Most scope creep claims aren’t about a design mistake. They’re about extra work, delays and money, and the defense often costs far more than the settlement. This session covers a tight scope, a change process written into the contract, and the paper trail that holds up later.

Watch by topic →Questions answered →

For architects, engineers and construction professionals · Hosted by Avi Rabbani, founder of Hardcover · Recorded March 29, 2023 · 68 minutes

68minute session with a carrier’s risk manager and a senior underwriter
11attendee questions answered live
11short episodes, each with a clip
800changes documented on one project, and why that record mattered
A change process that holds up

Five steps that keep extra work from becoming a claim

The panel’s advice came back to the same idea every time: decide how changes work before the first one shows up.

  1. Write the scope

    Say what you will do, and what you won’t. A clear scope is what every later argument comes back to.

  2. Set a threshold

    Agree in the contract on the level of change that adjusts your fee and schedule, so small asks don’t quietly add up.

  3. Talk early

    When a change comes up, raise it with the owner then, not at the next invoice.

  4. Log everything

    Record every change, paid or not. The log is what explains a slipped schedule years later.

  5. Put it in writing

    Confirm each fee or schedule change in writing, even a short email.

Most scope creep claims aren’t about a design mistake. They’re about extra work, delays and money, and the defense can cost far more than the settlement.
“A well written contract starts with a well defined scope of services.”A carrier’s director of risk management, in the session
Stories from the session

Four situations the panel walked through

Restroom renovation

The job worth walking away from

Declinethe risk manager’s advice, before any contract was signed

A client would only pay to renovate two of four restrooms, which conflicted with code and accessibility rules. The firm wanted the client to indemnify it. The risk manager pointed out that the likely claimant was a member of the public, so an indemnity from the client wouldn’t solve the problem.

If you know a design won’t meet code, a contract clause can’t fix it.

Oceanfront custom home

The site changed. The claim came anyway.

$10M+home value, designed years earlier

Years after the design, erosion changed the site. The design team was brought into a claim that the underwriter described as costly. She noted that, in general, the larger the house, the larger the claims tend to be.

High-value residential work carries high-value claims.

Landscape architecture

A planter that outgrew its pot

Paidthe claim was paid

A landscape architect specified decorative planters that cost thousands of dollars each. A plant outgrew its pot and broke it, the firm was sued, and the claim was paid.

What you specify and recommend is part of your design.

Delay claim defense

Hundreds of changes, none paid

800changes on one project, the panel’s example

Asked whether unlimited construction administration hours make tracking pointless, the risk manager said no. A record showing hundreds of changes explains why a schedule slipped, even if none of them earned a fee.

Keep the change log even when nobody is paying for the changes.

Contract fixes

Five wording changes the panel pointed to

Examples of the direction to go, not language to copy. Have your attorney fit them to your contract and your state.

Watch for · CodesA promise to comply with every code, or a fixed list of codes
Ask forReasonable professional efforts to meet the codes in effect when you design
Watch for · Liability capA cap of a set amount or your fee, “whichever is more”
Ask forA fixed number that is reasonable where you work, as low as the owner will sign
Watch for · ChangesNo way to adjust fee or schedule when the project changes
Ask forA change threshold that triggers a written fee and schedule adjustment
Watch for · Taking over a setSilence about another firm’s drawings you are finishing
Ask forA statement that you aren’t relying on the accuracy of documents prepared by others
Watch for · Pools and specialty itemsThe specialty designer hired as your sub-consultant
Ask forThe owner contracts with the specialist directly
Watch by topic

11 short episodes, one topic each

Each episode is a short clip from the recording with a written article. Start anywhere.

  1. Scope creep claims usually aren’t design mistakes

    Why extra work leads to delay and fee claims, and why defense can dwarf the settlement.

    ▶ 3:15 in the recording Article coming soon
  2. A good contract starts with a well-defined scope

    Written agreements, standard forms, and why a reused template needs a fresh look.

    ▶ 5:58 in the recording Article coming soon
  3. Don’t promise to meet a list of codes

    Should the contract list the codes you follow? Why broad wording works better.

    ▶ 13:18 in the recording Article coming soon
  4. Write a change process into every contract

    Fee and time flexibility up front, and how to stop death by a thousand cuts.

    ▶ 34:19 in the recording Article coming soon
  5. Document every change, paid or not

    Even with unlimited construction administration hours, the record is your defense.

    ▶ 50:41 in the recording Article coming soon
  6. Projects that stop and start

    Funding gaps, owner changes, long pauses, and what to put in the contract.

    ▶ 46:24 in the recording Article coming soon
  7. Your liability cap is a defense, not an opening offer

    Why a cap holds its ground, and why “whichever is more” limits nothing.

    ▶ 20:07 in the recording Article coming soon
  8. Taking over another firm’s drawings

    Becoming architect of record on someone else’s design means taking on their risk.

    ▶ 48:30 in the recording Article coming soon
  9. When bids come in over budget

    Who pays for value engineering and redesign, and how to contract for it.

    ▶ 1:03:57 in the recording Article coming soon
  10. Pools, planters and other small items with big claims

    What you specify is part of your design. When to have the owner hire a specialist.

    ▶ 54:02 in the recording Article coming soon
  11. The job worth walking away from

    A renovation where the client wanted to skip a code requirement.

    ▶ 10:16 in the recording Article coming soon
Q&A

10 questions, answered

What attendees asked during the session, and what the risk manager and underwriter said. The short answer comes first.

Asked live · 15:28

Can I list the specific codes I'll follow instead of agreeing to meet all codes?

The panel leaned toward keeping code language broad.

Read the full answer

Asked live · 44:05

Small requests keep turning into a lot of extra work. Is it fair to ask for more fee?

The risk manager said the contract governs this, so the key is getting changes written into it.

Read the full answer

Asked live · 50:41

Should we document every out-of-scope change, even with unlimited construction administration hours?

Yes.

Read the full answer

Asked live · 46:24

Our projects keep pausing for 2 to 6 months and restarting. Is a restart fee typical?

The panel said stop-and-start projects are very common and are leading to claims.

Read the full answer

Asked live · 48:30

An owner fired the last architect and wants us to finish from the existing drawings. What should we watch for?

The risk manager said he doesn't like this setup.

Read the full answer

Asked live · 63:57

Bids came in over budget. How do we make sure the client pays for redesign?

The risk manager said this comes down to what you agreed to up front.

Read the full answer

See all 10 questions →

Takeaways

Three things to take with you

01

Scope creep is a contract problem first.

A well-defined scope of services is what every later argument comes back to.

02

Write the change process in before work starts.

Build in fee and time flexibility, and a threshold that triggers a change in fee.

03

Document every change, paid or not.

The record of changes is what defends a delay or fee claim years later.

Hardcover’s founder, a Licensed Insurance Agent, with a carrier’s director of risk management and a senior underwriter. Stories are anonymized. This is risk management information, not legal advice; coverage depends on the terms of your own policy, and your attorney should review any contract before you sign it.