Power, generation, batteries and water: the new exposures

On a data center, the hardest problem is not the building. It is getting enough power to it, backing that power up, and cooling what it runs. Each of those brings exposures most building engineers have not carried before.

The constraint

Sites now follow the power

CBRE, a commercial real estate broker, named power availability and delivery timelines as the main constraints on where data centers are built in its first half 2026 report, with community acceptance now close behind.[1] That changes the engineer’s job. Power is no longer something the utility delivers to the property line. It is a design problem, a permitting problem and a schedule problem, and often all three on one project.

New capacity is slow to arrive. Berkeley Lab’s queue research found the median power project built in 2025 took 61 months from interconnection request to commercial operation.[2] Loads have their own queues: in June 2026 FERC ordered all six regional grid operators to justify or reform their rules for connecting large loads within 60 days.[3]

Owners respond by building their own generation and storage. That brings air permits, fuel, batteries and water into scopes that used to stop at the switchgear.

Six exposures

What is changing, and what can go wrong for the engineer

01

Utility interconnection

Berkeley Lab found the median power project built in 2025 took 61 months from interconnection request to operation, with 2,061 GW still waiting in queues.[2] Large loads like data centers face their own process, which FERC ordered all six regional grid operators to justify or reform in June 2026.[3]

Our practical view of the risk: A design built around a utility date or a capacity figure that later moves. Write down whose number it was.

02

Diesel generators

Backup generators need air permits: Virginia’s DEQ listed 177 data center air permits in November 2024, 85 of them in Loudoun County.[5] EPA clarified in 2025 that some emergency engines may run up to 50 hours a year in non-emergency conditions to support the grid.[4]

Our practical view of the risk: Generator counts, run hours and stack design that do not match the permit, or a permit assumption that fails.

03

Gas turbines on site

When the grid cannot deliver, some owners build generation. In Memphis, Shelby County issued an air permit in July 2025 for 15 gas turbines at xAI’s data center after the company had run turbines without one, and the permit drew an appeal before the county board upheld it.[6][7]

Our practical view of the risk: Emissions, permitting and neighbor claims on a scope that looks more like a power plant than a building.

04

Fuel cells

In November 2024, utility AEP signed an agreement for up to 1 GW of Bloom Energy fuel cells to power AI data centers, with a first order of 100 MW, according to Bloom.[8]

Our practical view of the risk: Newer technology, fewer reference projects, and gas supply and interconnection designs engineers may not have done before.

05

Battery storage

NFPA 855 governs the installation of stationary energy storage, with a 2026 edition now published.[9] Trade press reported the standard could change data center UPS designs, which depend on large battery banks.[10]

Our practical view of the risk: Room separation, detection and code edition questions, especially when lithium ion replaces older batteries in an existing room.

06

Cooling water

Berkeley Lab estimated US data centers directly consumed about 17 billion gallons of water for cooling in 2023, roughly triple 2014.[11] A law firm flags wastewater discharge from cooling systems as an environmental risk.[13]

Our practical view of the risk: Water supply, discharge and treatment assumptions, and pollution claims from releases.

Water and neighbors

Cooling water and community opposition

Berkeley Lab estimated US data centers directly consumed about 17 billion gallons of water for cooling in 2023, roughly three times the 2014 figure, and companies rarely disclose how much individual sites use.[11] Water now features in local fights over new projects. Data Center Watch, which tracks local opposition, counted at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026, the largest single quarter it had recorded.[12]

A law firm writing on data center risk notes that clustering projects where power and water are available also concentrates exposure to local regulatory challenges such as permitting delays, and flags cooling system wastewater discharge as an environmental risk.[13]

Our practical view: the engineer’s exposure here is less about the opposition itself and more about what the firm wrote down. A water demand estimate, a discharge assumption or a noise prediction made for a hearing becomes a document others rely on, and sometimes a document opponents test.

Liability and insurance

What each means for an engineer’s coverage

Professional liability. Power is the most common cause of serious outages, so electrical and generation design sits close to the costliest claims a data center produces.[14] Be aware that coverage is not uniform: Data Center Knowledge reports some technology E&O policies exclude claims arising from failure of power, utility or telecommunications systems.[15] Whether your own policy responds depends on its wording and the facts.

Pollution. Generator emissions, fuel storage, turbine permits and cooling discharge are pollution shaped exposures.[13][6] Our practical view: many professional liability policies limit or exclude pollution, so a firm designing these systems should ask its broker whether it needs contractors pollution or professional pollution coverage. See our environmental liability page.

Contracts that promise capacity. Our practical view: the riskiest sentence in a data center contract is one where the engineer guarantees a power or cooling result, a utility date or a permit outcome. Insurance generally covers negligence, not guarantees, so a promise beyond the standard of care can leave a firm holding a loss its policy was never written for. More in the clauses in hyperscaler and colocation contracts.

Our practical view

Five things to do before you design power

  1. Name the source of every power number in your design basis: utility letter, owner, or your own estimate.
  2. Do not promise capacity, a delivery date or a permit outcome. Design to the standard of care and say so.
  3. Ask whether your professional liability policy has a pollution exclusion, and whether you need professional pollution cover.
  4. If you design generation or storage, check that your application describes it. Carriers may treat it differently from building systems.
  5. Read the owner contract for performance guarantees, liquidated damages and consequential damages.

Schedule pressure on power is covered in speed to power: schedule pressure and delay claims.

For your firm

Designing generation, storage or substations?

Send us your policy and a description of the scope. We will tell you where pollution and power exclusions could bite.

Common questions

Data center power, in plain words

Why is power the main constraint on data centers?

Because new capacity takes years to connect. Berkeley Lab found the median power project built in 2025 took 61 months from interconnection request to operation, and a broker’s 2026 market report named power availability and delivery timelines as the main constraints on siting.

Who is liable if a data center loses power?

It depends on the cause, the contracts and the facts. Power is the most common cause of serious outages in Uptime Institute’s data, so the electrical design, the commissioning and the contract terms on consequential damages usually all come into it.

Does professional liability insurance cover pollution from generators?

Often not fully. Many professional liability policies limit or exclude pollution, and some firms add professional pollution coverage or an environmental policy. Whether a claim is covered depends on the policy wording and the facts.

Does NFPA 855 apply to data center UPS batteries?

It can. NFPA 855 covers stationary energy storage systems, and trade press has reported it could change data center UPS designs. Which edition and which sections apply depends on what the local jurisdiction has adopted, so check with the authority having jurisdiction.

Why are communities opposing data centers?

Water use, noise, power prices and land use are common complaints. Data Center Watch counted at least 75 projects worth about $130 billion blocked or delayed in the first quarter of 2026 alone.

Keep reading

Sources

  1. CBRE, North America Data Center Trends H1 2026 (a commercial real estate broker)
  2. Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition (interconnection queues as of the end of 2025)
  3. Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies” (a law firm, July 2026)
  4. US EPA, “EPA Issues Clarification to Help Power Data Centers” (2025, on emergency engine operating hours)
  5. Virginia Mercury, on Virginia DEQ’s public list of data center air permits (November 2024)
  6. E&E News, “Musk’s xAI gets air permit for Memphis supercomputer” (2025)
  7. Tri-State Defender, on the Shelby County Air Pollution Control Board upholding the xAI permit (December 2025)
  8. Bloom Energy, press release on its fuel cell agreement with AEP (a fuel cell maker, November 2024)
  9. NFPA 855, Standard for the Installation of Stationary Energy Storage Systems (2026 edition)
  10. Data Center Frontier, “New NFPA Battery Standard Could Impact Data Center UPS Designs”
  11. Civil Beat, reprinting The Conversation, “Data centers consume massive amounts of water, companies rarely say exactly how much” (2025)
  12. The Next Web, on Data Center Watch’s count of projects blocked or delayed in Q1 2026 (Data Center Watch tracks local opposition)
  13. Covington, “Data Centers: Emerging Risks and Insurance Coverage Considerations” (a law firm, 2025)
  14. Uptime Institute, Annual Outage Analysis 2025, press release (Uptime is a data center certification and advisory firm)
  15. Data Center Knowledge, “Managing risk: is your data center insurance up to the test?”

General information only, not legal advice, current as of November 2026. Interconnection rules, air permit guidance and fire codes change, and the edition that applies depends on your jurisdiction. Whether a claim is covered depends on the facts and your actual policy wording.