Speed to power: schedule pressure and delay claims

A data center earns nothing until it is energized and a tenant is running. That puts every party under schedule pressure, and when the date slips, the owner looks for someone to pay for it. Here is how delay claims reach designers, and how to keep the ones that are not yours away from you.

The pressure

Fast-track, phased and always changing

Crowell & Moring, a law firm, writes that under the pressure on these projects the cost of data center construction delays can be exorbitant, and that compressed timelines have pushed delivery toward modular and prefabricated methods.[1] The AGC, the contractors’ association, notes that specialized equipment and labor raise the risk of supply chain delay and labor shortages, and that ordering equipment early to avoid delay carries risks of its own.[2]

For engineers, our practical view is that the pressure shows up in three ways. Design is issued in packages while later packages are still being drawn. The basis of design moves because the tenant, the chip generation or the cooling method changes. And equipment is bought before the design that depends on it is final. Each of these is normal on a data center. Each is also where an owner will later look for a design error to explain a late date.

Long-lead equipment

Transformers, switchgear and generators

Wood Mackenzie’s supply chain survey put average lead times for power transformers at 128 weeks in the second quarter of 2025, with generator step-up transformers at 144 weeks and switchgear at about 44 weeks.[3] It projected a 2025 supply shortfall of about 30% for power transformers and 10% for distribution transformers.[4] A transformer supplier quotes higher figures for data center class switchgear, 52 to 84 weeks and more, based on contractor quotes.[5] For larger generator packages, POWER Magazine reports lead times of up to a year or more.[6]

Two things follow for a designer. Equipment is often selected and released before your design is complete, so your design has to fit what was bought. And when a substitution is made because the specified item is not available, your review of it takes time and can change the design around it. Both are easy to absorb in a fee and a schedule if the contract says so, and hard to recover if it does not.

Cause matters

Delay caused by design, and delay caused by supply

Delay claims turn on cause. Many EPC (engineer, procure, construct) and CM-at-risk contracts treat broad categories of supply chain disruption as excusable but noncompensable: the contractor gets time, not money, unless it negotiated cost relief.[7] Reed Smith, a law firm, advises owners to allocate supply chain risk expressly so no one can later say it was never contemplated.[8]

Delay caused by design is different. A late drawing package, a slow submittal review, or an error that forces rework can lead to a claim against the engineer by the owner, and through the owner by the contractor. Our practical view: the defense is usually the record. Owner decisions that arrived late, basis of design changes, and equipment substitutions you did not make are each reasons the date moved that have nothing to do with your care. If they are not documented as they happen, they are hard to prove a year later.

Liquidated damages and insurance

How professional liability treats delay and LDs

Liquidated damages are an amount per day of delay, fixed in the contract in advance. When one appears in a design agreement, it deserves a hard look. NSPE has argued that a liquidated damages clause is not appropriate for design services, that it jeopardizes the coverage available under a professional liability policy, and that it can pressure engineers to issue incomplete documents to meet a date. It suggests the engineer’s obligation be to perform as expeditiously as is consistent with professional skill and care.[9]

The reason is the contractual liability exclusion. Professional liability policies commonly exclude liability a firm assumes by contract unless the firm would have been liable without the contract.[10] An LD is owed because the contract says so, whether or not anyone was negligent. One court, in a case discussed by The D&O Diary, said a party that agreed to liquidated damages had “effectively contracted out of its insurance coverage.”[11] That case involved a different kind of policy, but the logic is the one a professional liability insurer will apply.

A delay claim based on negligence is different. If an owner can show that your negligence caused the delay and the loss, that is the kind of claim professional liability insurance is built for, subject to the policy terms and to any consequential damages waiver, since lost rent and lost revenue are typically consequential. Whether any particular claim is covered depends on the policy wording and the facts.

Our practical view

Six things to put in your contract

01

Schedule as a standard of care

Agree to perform as promptly as is consistent with professional skill and care, not to meet a date. NSPE suggests this wording for design services.

02

No liquidated damages on design

Strike LDs from your agreement. If the owner insists, cap them, make them the sole remedy for delay, and tie them only to milestones you control.

03

Owner decisions with dates

List the decisions you need (equipment selections, tenant loads, cooling method) and the dates you need them. A late decision is the owner’s delay, but only if the dates were written down.

04

Changes are changes

Every new rack density, tenant fit out or substituted equipment item is additional service with a fee and a schedule adjustment.

05

Supply is not design

Say that you are not responsible for manufacturer lead times, allocation or delivery, and that substitutions you did not specify require your review time.

06

Mutual consequential waiver

Lost rent, lost revenue and tenant penalties from late delivery are consequential damages. Waive them both ways.

For your firm

Is there an LD clause in your agreement?

Send it to us before you sign. We will tell you how your professional liability policy is likely to treat it, and what to ask for instead.

Common questions

Delay and LDs, in plain words

Does professional liability insurance pay liquidated damages?

Often not, but it depends on the wording and the facts. Liquidated damages are owed because a contract says so, not because someone was negligent, and professional liability policies commonly exclude liability assumed by contract beyond what the law would impose. NSPE has warned that an LD clause in a design contract jeopardizes the coverage available.

Can an owner sue the engineer for delay without an LD clause?

Yes, if the owner can show the engineer was negligent and that the negligence caused the delay and the loss. That is the kind of claim professional liability insurance is built to respond to, subject to the policy terms and any consequential damages waiver in the contract.

If the switchgear is a year late, is that my problem?

Usually it is a supply problem, not a design one. Many construction contracts treat supply chain disruption as excusable delay without extra pay, but it depends on the clause. Make sure your own contract says you are not responsible for manufacturer lead times.

Is there insurance for liquidated damages?

There is a market for it. Marsh, a broker, offers liquidated damages insurance for data center construction delays. It is typically bought by the parties carrying the LD obligation, not by design firms, and terms vary.

Keep reading

Related

Sources

  1. Crowell & Moring (a law firm), “Data center risks include schedules, supply chain, labor” (Law360)
  2. AGC of America, “Insurance Issues in Constructing Data Centers: A GC’s Perspective”
  3. Wood Mackenzie, “Making the connection” executive summary, September 2025 (published by POWER Magazine)
  4. POWER Magazine, “Transformers in 2026: shortage, scramble or self-inflicted crisis?”
  5. Giga Energy, “Lead time delays for data centers” (a transformer supplier)
  6. POWER Magazine, “Data centers are turning to gas generators for prime power to eliminate long lead times for grid connections”
  7. ABC of the Carolinas (a contractors’ association), “Construction delay claims: tightening contract risk in the Carolinas”
  8. Reed Smith (a law firm), “A toolbox for managing supply chain problems in construction contracts”
  9. NSPE, PE Magazine, “The Client: Liquidated damages give reason for caution”
  10. EJCDC, Contract Insurability Negotiation Guide
  11. The D&O Diary, “Thinking about the contractual liability exclusion” (a blog written by an insurance broker executive)
  12. Marsh (a broker), “Liquidated damages insurance for data centre construction delays”

General information only, not legal advice, current as of November 2026. Lead times change quickly and the figures above are dated to their sources. Whether a claim is covered depends on the policy wording and the facts. Have counsel review your contract.