Projects that pause and restart are common, and they are leading to claims. When an owner runs out of funding or ownership changes, the owner may later blame the design firm for the delay. Your contract and your records are what help most.
Why projects stop and start
An attendee raised a pattern many firms know. Their jobs kept starting, stopping, starting and stopping again. Most pauses lasted 2 to 6 months. A carrier risk manager on our panel called it a good question. He said stop-and-start projects are very common and are leading to claims.
He described a few reasons projects stall:
- The owner runs out of funding.
- The project changes owners.
- The owner switches design professionals, so a new firm picks up the work midway.
How a pause turns into a delay claim
The pattern he described goes like this. A project is shut down for months. Then the owner comes back and says that if the work had been done on time, they wouldn’t have had all these costs. In their telling, the pause becomes your fault.
Picture this. An owner pauses a project while they look for new financing. Months later, work starts again, and the opening date has slipped. The owner says your drawings were late and that is why the project cost more. That is a delay claim: a claim that slow work cost the owner money. The first episode explains why scope creep claims usually aren’t design mistakes.
Is a restart fee typical?
The attendee asked whether a restart fee is typical. The panel did not name a standard restart fee or a typical amount. That doesn’t mean you can’t ask for one. It means the answer depends on what your contract says. If you want one, raise it in the proposal, while the owner is still deciding. It is a harder ask once the project has already paused.
A restart takes real work. Your team has to get back up to speed, check what changed and update the drawings. The broader advice from the webinar applies here: build fee and time flexibility into the contract. That is covered in write a change process into every contract.
Contract terms to think about for pauses
Before you sign, think about what happens if the project stops. This list is Hardcover’s own, not the panel’s. These are questions to talk through with your attorney, not standard terms:
- How long can the project pause before your fee or schedule is revisited?
- Who pays for the work to restart after a long pause?
- Does the schedule extend by the length of the pause?
- Can you end the contract if the pause runs too long?
A pause is a change, so treat it like one
Many firms think of a pause as time off from a project. It is better to think of it as a change. The schedule moves, the team moves on to other work, and the project you return to may not be the one you left.
Picture this. A project stops for five months. When it restarts, the owner wants to keep the old deadline. Your change process, if you have one, is what lets you ask for more time and fee without starting a fight.
Keep records of every stop and restart
The panel’s advice to document every change, paid or not applies to pauses too. Write down when the owner stopped the project, why, and when they asked you to start again. Keep the emails.
If the owner later says you caused the delay, those dates tell a different story. A pause the owner called is harder to blame on you when it is in writing. For what happens once a claim is filed, see how a professional liability claim unfolds.
When you’re the new firm
Sometimes the restart comes with a new design team. If the owner switched firms, you may be the one picking up the work midway. That brings its own risks, covered in taking over another firm’s drawings.
A pause you didn’t cause can still become a delay claim, so put restarts in your contract.
Common questions
Can I charge a restart fee after a long pause?
The panel didn’t name a standard restart fee. Whether you can charge one depends on your contract, so it helps to address pauses before you sign.
Can an owner blame me for a delay they caused?
They may try. Records of when the owner paused and restarted the project can help show what really caused the delay.
This is risk management information, not legal advice. Have your attorney review any contract before you sign. This article is general information, not insurance or legal advice. Coverage depends on the terms, conditions and exclusions of your policy as issued, and every firm’s price is set by the insurer on its own facts.