Once a contract is signed, it can be very hard to renegotiate. That’s why the contract itself should say how fees and schedule change when the work changes. It should also say what level of change triggers it.
Contracts are hard to change once signed
Hardcover’s founder cited a risk management resource on this. Once a project begins, it is nearly impossible to renegotiate the agreement, unless the agreement already allows terms to be revisited. After signing, the client has what they want, and you have little to bargain with.
A carrier risk manager on our panel said scope creep is inevitable. The more complex the project, the more changes and change orders you will see. A change order is a written agreement to change the work, the fee or the time. So your contract should give you room to raise your fee and extend your time.
What a change process covers
The risk manager said the contract governs this, so get the change process written into it. Based on the panel’s advice, it should give you:
- A way to raise your fee when the project gets more complex.
- A way to raise your fee when it takes more time.
- A way to raise your fee when it needs another set of drawing changes.
- More time on the schedule when the work grows.
- A set level of change that triggers a fee change.
Unpaid extra work can become a fee dispute
When extra work goes unpaid, it can turn into a fee dispute. The firm feels it did more than it agreed to. The client feels it already paid for the job. Read how one fee dispute claim played out.
A written change process keeps that argument small. Both sides agreed to the rules before anyone was upset.
Death by a thousand cuts
An attendee described the problem well. Small requests come in one at a time. Each one seems too minor to charge for, and nobody wants to look like they’re nickel-and-diming the client. Together, they add up to a lot of unpaid work. The attendee called it death by a thousand cuts.
The risk manager said not every change needs to add a fee. A contract can set a level of change that does. For example, you might agree that small tweaks are part of the fee, but a change that needs a new set of drawings is billed as extra. You don’t send a bill for every phone call, and the client knows where the line is before it is crossed.
Inexperienced owners need it most
Some owners haven’t built much before. The risk manager named municipalities, nonprofits and volunteer boards as common examples. These owners may not understand how projects change along the way. If the contract doesn’t address change, he said, that’s where firms run into trouble.
These owners can also be harder to negotiate with. That makes it more important to settle the change process before signing, because you may not get another chance.
Unknowns you can’t see at the start
Some changes have nothing to do with what the client wants. The site itself can surprise everyone. The risk manager gave examples like soil problems found mid-project, or sinkholes in places like Florida. One discovery like that can change the whole project.
A change process gives you a fair way to handle the new work. Without one, you may be stuck choosing between a free redesign and an argument with the owner.
Tools firms already use
In the chat, attendees said they already use additional services provisions and stop-work clauses. An additional services provision says work beyond the scope is billed separately. Our glossary explains additional services. A stop-work clause lets you pause work in set cases, such as unpaid invoices, depending on its terms.
Coordination with subconsultants and contractors is another place scope creep shows up. The risk manager called it a topic of its own. Whatever tools you use, a change process works best with a paper trail. See document every change, paid or not and projects that stop and start.
Agree on how changes get paid before the first change shows up.
Common questions
Do I have to charge for every small change?
No. The contract can set a level of change that triggers a new fee. Small requests stay within your fee, and bigger ones get billed.
What if the contract is already signed?
It can be hard to renegotiate. Talk with the owner when changes come up, and document every change so the record shows what happened.
This is risk management information, not legal advice. Have your attorney review any contract before you sign. This article is general information, not insurance or legal advice. Coverage depends on the terms, conditions and exclusions of your policy as issued, and every firm’s price is set by the insurer on its own facts.