Document Every Change, Paid or Not

From the webinar Managing Scope Creep · Episode 5 of 11

Short answer

Write down every change to the scope, even the ones you aren’t paid for. If a delay claim comes later, that record can help show why the schedule moved.

Unlimited hours don’t remove the need for a record

An attendee asked a practical question. Their agreement allowed essentially unlimited construction administration hours. That is the work you do during construction, like answering contractor questions and reviewing submittals. Since those hours were already in the fee, did they still need to document changes outside the scope as additional services?

A carrier risk manager on our panel said yes. Document all changes, whether or not you are paid for them.

It is easy to see why the question comes up. If you can’t bill for a change, writing it down feels like extra work for nothing. The risk manager’s answer was that the record has a value that has nothing to do with billing.

Why the record matters in a delay claim

In the first episode, the risk manager explained that many claims against design firms are delay claims. The owner says late work hurt their profits. The question becomes why the project ran long.

His example: say there were 800 changes during a project. If you face a delay claim later, a record of those changes can help show why there was a delay. That holds even if none of them earned you extra pay. Without the record, it is your memory against the owner’s.

Claims can come long after a project ends. By then, people have moved on and emails are hard to find. A change log written at the time is far easier to rely on. See how a professional liability claim unfolds for the steps.

Talk with the owner when changes come up

The risk manager also said to have the conversation with the owner when changes come up. Don’t let a change slip by because it feels small or awkward to raise. Talk about it, then make sure it is well documented. If the owner says no to an extra fee, write that down too. The change still happened, and it still took time.

A short talk at the time of the change often goes better than a long argument at the end. The owner hears about the change while it is fresh. You get a chance to agree on time or fee before the work is done. The episode on writing a change process into every contract covers how to set this up before you sign.

What to write down for each change

This list is Hardcover’s own suggestion, not something the panel laid out. Keep each entry to facts and dates:

  • What changed, in a sentence or two.
  • The date of the request.
  • Who asked for it.
  • The expected effect on the schedule.
  • Whether it affects your fee, and whether you billed it.
  • Any reply from the owner.

Keep it to facts

Leave out opinions and blame. A plain record is easier to rely on than one that reads like an argument. If a dispute comes up, someone outside the project may read every word.

For example: “Owner asked to move the stair to the north wall on March 3. Adds about two weeks to the drawings.” That entry is short, dated and clear. Anyone reading it later can see what happened and when.

Emails count as part of the record too. Our page on engineering emails as documentation explains why the way you write them matters.

Simple habits for your team

A change log only helps if people keep it up. Make it part of how your team works, not a task for the end of the project. A few habits we suggest:

  • Keep one change log per project, in one place everyone can find.
  • Log a change the same day it comes up.
  • Send the owner a short email confirming the change.
  • Review the log at each project meeting.
  • Log pauses and restarts too, as covered in projects that stop and start.
The change you didn’t bill for may be the one that explains the delay.

Common questions

Why document a change I’m not charging for?

Because it can explain a delay later. If an owner says your work was late, a record of every change helps show why the schedule moved.

What should a change log include?

Keep it to facts and dates: what changed, when, who asked and the effect on time. Plain entries written at the time are easier to rely on later.

This is risk management information, not legal advice. Have your attorney review any contract before you sign. This article is general information, not insurance or legal advice. Coverage depends on the terms, conditions and exclusions of your policy as issued, and every firm’s price is set by the insurer on its own facts.

Talk to a specialist

Questions about your own contract or coverage?

Send us the contract’s insurance section or your declarations page. We’ll tell you what we see. Insurance guidance, not legal advice.

Free, no-obligation coverage review. If what you have already fits, we’ll tell you.

CallGet a Quote →