Scope Creep

Work that grows beyond what the contract describes, often through small requests that add up, without a matching change in fee or schedule.

What it means for your firm

Many scope creep disputes are about fees and delays rather than a design mistake. A well-defined scope of services, a written change process and a record of every change, paid or not, are the usual defenses.

General definition for education only. It is not an interpretation of any policy or contract, and it is not legal advice. The wording of your own policy and contract controls. Policies and definitions vary by insurance company.

Field notes

What we saw this year

From real claims we handled and our sessions with underwriters. Every client is anonymized.

What underwriters are seeing

Most scope creep claims aren’t design mistakes

A carrier’s risk manager told our session that scope creep claims are usually about extra work, delays and money rather than a design error, and that defense can cost far more than the eventual settlement.

A tight scope and a written change process do most of the work.

Managing Scope Creep webinar, March 2023
Asked and answered

Document every change, paid or not

Asked whether unlimited construction administration hours make tracking pointless, the panel said no: a record of every change, even hundreds of small unpaid ones, is what explains a slipped schedule when a delay claim arrives.

Keep the change log even when nobody is paying for the changes.

Managing Scope Creep webinar, March 2023
Talk to a specialist