Asked live · 15:28 in the recordingQ Can I list the specific codes I'll follow instead of agreeing to meet all codes?
A The panel leaned toward keeping code language broad.
The panel leaned toward keeping code language broad. Hardcover's founder noted that codes change often, in some states every couple of years or after a major storm, so a fixed list can go out of date. A carrier risk manager added that not every code is completely clear, and a flat promise to comply can be used against you later. The middle ground discussed was agreeing to do your best to comply, rather than a 100% contractual guarantee. And if you know a design won't meet code, the advice was not to go ahead just because the client asks.
Link to this answer
Asked live · 44:05 in the recordingQ Small requests keep turning into a lot of extra work. Is it fair to ask for more fee?
A The risk manager said the contract governs this, so the key is getting changes written into it.
The risk manager said the contract governs this, so the key is getting changes written into it. Not every small change has to trigger a new fee. A contract can set a level of change that does, which protects you from slow, steady scope growth without seeming to nickel-and-dime the client. When the project becomes more complex or time-consuming, or needs another round of drawing changes, you should have a written way to raise your fee. He noted that unknowns, such as soil problems found mid-project, can change an entire job.
Link to this answer
Asked live · 50:41 in the recordingQ Should we document every out-of-scope change, even with unlimited construction administration hours?
A Yes.
Yes. The risk manager said to document all changes, whether or not you're paid for them. If you later face a delay claim, a record showing, for example, 800 changes during the project can help explain why the schedule slipped, even if none of them earned an extra fee. He also suggested talking with the owner each time a change comes up and making sure it's all well documented. Unlimited hours in the contract don't change the value of the record.
Link to this answer
Asked live · 46:24 in the recordingQ Our projects keep pausing for 2 to 6 months and restarting. Is a restart fee typical?
A The panel said stop-and-start projects are very common and are leading to claims.
The panel said stop-and-start projects are very common and are leading to claims. Owners run out of funding, ownership changes, or a new design team comes in, and when work resumes the owner may argue that the delay cost them money. The panel didn't name a standard restart fee. The advice centered on the contract: build in the right to adjust fee and schedule when the project changes, and keep a written record of every pause and change so you can show why time was lost.
Link to this answer
Asked live · 48:30 in the recordingQ An owner fired the last architect and wants us to finish from the existing drawings. What should we watch for?
A The risk manager said he doesn't like this setup.
The risk manager said he doesn't like this setup. Picking up another firm's drawings is like editing an article someone else wrote: errors can be harder to spot than if you started from scratch, and owners often ask because they don't want to pay for a new set. At the least, get written language saying you aren't relying on the accuracy of the earlier drawings. Even then, you're still buying risk. You may be pulled into a lawsuit and have to use that clause as a defense to get out. Weigh what you're being paid against that risk.
Link to this answer
Asked live · 63:57 in the recordingQ Bids came in over budget. How do we make sure the client pays for redesign?
A The risk manager said this comes down to what you agreed to up front.
The risk manager said this comes down to what you agreed to up front. If you already committed to a contract and a fee and the numbers come in higher than expected, the extra work can leave you underpaid; that's the risk of not having pricing settled when you signed. For construction pricing, he said the better setup is for the owner to contract separately with the contractor, so cost overruns are the owner's problem rather than the designer's. He noted that cost overruns have led to claims.
Link to this answer