When Bids Come In Over Budget

From the webinar Managing Scope Creep · Episode 9 of 11

Short answer

If bids come in over budget and you’ve already agreed to a fixed fee, redesign work can leave you underpaid. The panel’s advice was to keep construction pricing between the owner and the contractor, not inside your contract.

The problem: redesign on your fee

An attendee asked a question many firms face. A project goes out to bid to stay within a budget, and the bids come back higher. The owner wants the design changed to bring the cost down. How do you make sure the client pays for that value engineering or redesign?

Value engineering means changing the design to lower the cost while keeping what the project needs. Our glossary explains value engineering. A carrier risk manager on our panel said the answer is part risk management and part underwriting.

Two versions of the same problem

He first read the question as being about subconsultant pricing. In that version, your subconsultants’ bids come in higher than you expected as the prime designer. If you have already agreed to a contract and a price with the owner, you will be underpaid. He said that is the risk of not having fixed pricing in place when you signed.

One way to act on his point is to get firm prices from your subconsultants before you set your own fee. Then the number you give the owner is built on numbers you already have.

The attendee clarified that they meant contractor pricing for construction. That is a different problem with a different answer.

Both versions start the same way. The price comes in higher than planned, and someone has to do more work to fix it. The question is whether your contract says who pays for that work.

Why a fixed fee leaves you exposed

This part is Hardcover’s view, not the panel’s. A fixed fee assumes a fixed amount of work. Redesign after high bids is new work. If your contract doesn’t say how that work gets paid, you may end up doing it for free.

It is the same idea behind writing a change process into every contract. Agree before signing how redesign is billed and what triggers it. For example, your contract could say one round of changes after bidding is part of the fee, and more rounds are billed as extra. For more on billing extra work, see our page on an additional services dispute.

Let the owner hold the contractor relationship

For construction pricing, the risk manager said you’d rather have the owner contract separately with the contractor. Then cost overruns are the owner’s problem, not the prime designer’s.

Picture this. You agree to deliver a project within a set construction budget, and the contractor works under your contract. Bids come in high, and now the overrun is tied to you. If the owner hires the contractor directly, the price is a matter between the two of them.

The owner and the contractor are the ones who agree on the price to build. Keeping that line clear in your contract keeps your fee tied to your design work. Ask your attorney how to word that split for your projects.

Cost overruns can become claims

The risk manager said cost overruns have led to claims. An owner who expected one price and got another may look for someone to blame. A clear contract, with a clear line between design fees and construction pricing, can help keep that from landing on you.

Bring up the budget early and often. If you see the design drifting above the owner’s number, say so in writing. That record can help show you raised the issue before bids came in. Money disputes can grow fast once a project goes over budget. Read how one fee dispute claim played out. For more detail on this topic, see our page on cost opinions and bids over budget.

Keep construction cost risk with the owner, and agree up front how redesign gets paid.

Common questions

Do I have to redesign for free if bids come in high?

It depends on your contract. If it doesn’t say how redesign gets paid, you may have little room to bill for it. Our page on cost opinions and bids over budget covers this in more detail.

Why should the owner contract directly with the contractor?

So cost overruns stay the owner’s problem. When the contractor works under your contract, the overrun can become tied to you.

This is risk management information, not legal advice. Have your attorney review any contract before you sign. This article is general information, not insurance or legal advice. Coverage depends on the terms, conditions and exclusions of your policy as issued, and every firm’s price is set by the insurer on its own facts.

Talk to a specialist

Questions about your own contract or coverage?

Send us the contract’s insurance section or your declarations page. We’ll tell you what we see. Insurance guidance, not legal advice.

Free, no-obligation coverage review. If what you have already fits, we’ll tell you.

CallGet a Quote →